Most of what we build is pipe, valve stations, pump houses and gun installs for ski areas across northern New England. Our crew work at Northeast ski areas in the winter and build for Summit all summer, so they know what these systems are like to run. In 2025 alone we put more than 54,000 feet of steel pipe in the ground across six mountains. Here are a few of those jobs. Have something similar coming up? Email Doug at doug@summitresourcesne.com.

Weld, transport and install 10,000 feet of steel pipe from base to summit. Install hydrant sets and multiple valve stations. Remove and cut all old pipe for scrapping.

Weld, transport and install 25,000 feet of steel pipe. Replace feed lines leaving main pumphouse. Relocate various lines to tie-into new return lines. Replace all supply and discharge piping in pumphouse. Add new 3rd booster pump. Install 9 SMI fan guns. Various heavy hauling of materials up the mountain.

String and install 11,600 feet of steel pipe on Sunset & Loon Mountain Park trails. Fabricate & install 2 new valve stations. Assist with concrete hauling. Install mix of traditional and HKD Klik hydrants.

String and install 2,850 feet of steel pipe. Install new valve station in base area.

Replace discharge side feed line in pumphouse. String and install 2,500 feet of 12" 0.500" steel pipe. Dig through technical base area utilities. Install new valve station.

Weld and install 2,700feet of steel pipe. Install various valve sets. Install hydrants. Dig and backfill.